How to make garage from profile pipe with own hands

It is possible to construct garage the hands, using profile pipe. Any sheet material, for example, the pro-thinned-out leaf will be suitable for covering and finishing. Such simple building is built quickly and perfectly copes with the tasks.

Design of garage from profile leaf

Before construction it is necessary to make the drawing of garage. It is necessary for calculation of the necessary material and the number and tracking all stages of work. The size of garage depends on the brand and parameters of the car and also on whether it is going to store tools there.

When planning it is necessary to consider that width of garage has to be one and a half meters more than the machine (and it is better to leave also additional space). Length is projected 2.5 meters more, than at the car.

Influences the scheme and features of material – the pro-thinned-out pipe. Planning the room, calculate that longitudinal pipes were located completely, there was no need to twist them or to weld. On way of assembly the garage can be welded or modular. The first type gathers quicker and it byudzhetny, but the device for welding is required here and ability to work with it. For the combined, modular building it is required to buy several additional brackets. But even one person can collect this look, such garage can be transported or changed its parameters.

Tools and materials for garage

For construction of frame garage it is necessary to take metal rolling by parameters about 10*10 cm. It will go to the main guides. Other elements can be done of pipes of the smaller size.

For covering of roof it is possible to use the pro-thinned-out sheets of any color or metal tile. Material has to be reliable and not pass moisture.

From tools the tape measure not less than 10 meters long for measurement of long pipes, drill with drills for work on metal, the Bulgarian with disk for metal rolling cutting, marker for marking and metalwork keys for twisting of bolts and nuts is required.

Do not forget to put on goggles and gloves to avoid injuries.

Construction of garage from professional pipe

The first stage of construction – designing of the base. Reinforced concrete, monolithic or continuous footing, pile or column will approach. At the same stage it is necessary to think of sexual covering in future garage. Here too it is possible to use monolithic reinforced concrete slabs or paving slabs which can be laid independently, and then it is easy to collect.

First of all it is necessary to clear away site under garage, to put away from there all construction debris and vegetation. Then to execute site marking, using the drawing. To dig out holes for columns at the edges of construction and on the center of long walls. In the depth of holes to make pillows of sand and crushed stone, having filled several layers of this mix there, to execute waterproofing from leaves of roofing material and to lay out rod posts from slag stone.

The next stage – creation of framework. The skeleton needs to be made of profile pipe with square section. From two long and two short pipes to collect the lower binding of garage, then to bolt it among themselves and to fix on the base by means of the used anchor bolts. To establish on each side vertical rails, connecting special fastening elements. To strengthen angle units hay crops from the pro-thinned-out pipe of smaller section and to establish the top binding. To fasten in the right places of stiffening fin and to make diagonal hay crops.

Then it is possible to start installation of gate. To make two rectangles which will become piles of products of suitable section. Strengthen shutters hay crops and stiffening fins. In addition make gate for pedestrian pass in one of shutters. To hang up shutters on garage framework, using 4 or more loops. To sheathe shutters metalprofile.

When the design is ready, to start covering. First of all, it is important to choose the correct material. The professional flooring with marking of C20 and more will approach. Also width between fillets is important. Special grooves allow to delete excess moisture quickly. You should not choose too heavy external covering. Better the professional flooring covered with polyurethane or polyester approaches. Attach each sheet to framework and fasten it the self-tapping screw. Carry out the movement in deflection of profile leaf to receive strong fastening and not to break tightness. On 1 m of wall 6-8 self-tapping screws there are enough.

The next important stage – roof. It is carried out from 4 farms which lift on the top binding of design. The roof can be made lean-to or twin (the first option is simpler and it is available even to beginners). For single-pitch roof the front wall becomes above back, and side are under construction with bevel. On this bias the rain or melt water will flow down.

The pro-thinned-out sheets or tile will be suitable for roof. Roof edges have to be given over walls approximately on 30-40 cm that the melt water did not leak under the base of the building.

Before use the garage needs to be warmed. Thin walls from metal badly keep heat therefore in the winter in such garage it will be cold. Mineral wool will be suitable for warming. This material of excellent holds heat and does not ignite.

Process of warming of garage of profile pipe begins with drawing on framework of waterproofing material. As protection against moisture the polyethylene film, polymeric membrane or other materials used for warming of residential buildings will approach. It is just pasted on framework or use special self-tapping screws with wide hats from plastic.

On this film it is necessary to fix furring in the form of rails. They are located vertically. In certain cases it is possible to miss this process – the framework of garage will cope with the supporting role. In this case waterproofing material should be put before mounting professional sheets, from outer end of framework.

Between rails of furring mineral mats are inserted. This heater can compress under external influence, and then take the initial form therefore width of elements have to be more, than distance between framework rods. Over heater the additional layer of waterproofing is put.

Completes process of construction after which it is possible to start arrangement, internal covering of garage. For this purpose it is possible to use plywood boards or plastic which are easily purified and it is not subject to moisture influence.

Author: «MirrorInfo» Dream Team