How to connect electricity at the dacha

How to connect electricity at the dacha

Connection of the seasonal dacha to the central power line perhaps after obtaining permission at suppliers of electrical energy. Permission is given on the basis of the submitted documents and the statement after receiving specifications.

It is required to you

  • - statement;
  • - documents of title on the site;
  • - passport;
  • - specifications;
  • - permission;
  • - contract for connection to the central power line;
  • - metering device;
  • - cable;
  • - corrugated pipe;
  • - anchor hook.

Instruction

1. To get permission to connection of electricity, address to regional management of the company delivering energy resources. Submit the application, specify data of the owner, the address or number of the seasonal dacha. Also it is necessary to specify in the statement what power of energy consumption will be required to you. If you use standard set of electric devices, it is enough to specify the required power of 5 kW. For connection of circular saw, use of the welding machine and other powerful electric devices specify 10-12 kW.

2. Except the statement you will need documents of title on the seasonal dacha. Submit all documents to Quality Department. Specifications make out from one to two months. Terms depend on the region of application.

3. You can conduct mounting and connection on the most seasonal dacha independently. For direct connection to the central power line you have to invite team of electricians from the supplying company.

4. For electricity supply to the seasonal dacha you will need the isolated copper cable with a section of 3 kW, corrugated pipe longwise of cable, anchor hook, the metering device of electrical energy.

5. The electric counter has to correspond to state standard specification and have the certificate allowing use of the device in the territory of the Russian Federation. Buying it in shop, pay on it special attention.

6. After connection to the power line install the counter and make internal distributing in the country house. If you have no lodge, and you carry out the electric power on the site, except the counter you will need to buy metal assembly box with the lock where the metering device will be installed.

7. The final stage of connection is commissioning and execution of the contract for electrical supply. For drawing up the act of commissioning of the metering device of the electric power invite the authorized representative from the Energonadzor.

8. With the received act address to customer department and sign the contract.